I. Senior seminar with the headmaster - September, 2009
II. Initial planning meeting with advisor - September 4, 2009
III. Present the advisor with a project proposal and preliminary plan for approval - October 2, 2009
IV. Written, personal and project narrative - November 6, 2009
V. Completion of a preliminary meeting with Guidance Counselor to discuss the “Senior Career Plan”
- December 4, 2009
VI. First presentation of project and portfolio to advisor including the completion of any three
components - December 4, 2009
VII. Subject area for senior project lock-in date - January 8, 2010
Only minor changes in project subject area are allowed after this date.
VIII. At least twenty hours of Community Service Completed and documented - January 8, 2010
IX. The completion of 10 or more components and a meeting with advisor to finalize project plans
- February 4, 2010
X. Completion of required community service component – March 5, 2010
XI. Completion of all components and all projects unless special permission has been
given by the Headmaster or Assistant Headmaster - March 25, 2010
XII. One copy of the entire portfolio written material submitted to the advisor for review and the
Scheduling of a required rehearsal presentation
(If this is not done then the student will not be scheduled for exit interview) - March 31, 2010
XIII. Four finished copies of portfolio materials present to advisor - April 2, 2010
XIV. Exit Interview - to be scheduled during early May.